UPHELD

Cardinal Development Co. v. Stanley Constr. Co.

UPHELD status graphic: Cardinal Development Co. v. Stanley Constr. Co.. 971001 Cardinal Development Co. v. Stanley Constr. Co. 02/27/1998 In an action for breach of a construction contract, the developer's agreement to pay for additional work along with the construction company's actual performance of that work constitutes valuable consideration sufficient to modify the original contract. It cannot be said that the trial court's award of damages to the construction company is plainly wrong or without evidence to support it, and its judgment is affirmed.